Barn Slab:
Total yards = 45 yards in 5-yard pours.

The five-yard pours were required so that ranch equipment could be moved between sections and then moved onto the cured concrete. The Project spanned three weeks between other work projects.

“The C.U.B.E. 150 worked great for my needs. I could only pour a few yards before moving equipment between the individual stalls. A transit-mix truck would have been tough to schedule and the C.U.B.E. 150 let me mix when I needed it.”

Estimated Cost Savings: $2,475.